Overview

Reclamation work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Notify Us

Click on Notify Us above to tell us about anything on your property or street related to the current projects.

Contacts

Links

Updates

Click on your street segment on the map below or see below for the latest update. 

July 11, 2019

The contractor is continuing grading in Phase 2 until complete.  Paving the first layer of asphalt is tentatively scheduled for late in the week of July 15, 2019 or early in the week of July 22, 2019.  The final layer of asphalt on all project areas is tentatively scheduled for mid to late August 2019.